November 5, 2026
Crews from RTC Washoe won't close the Sierra Street Bridge until early 2027. Even so, the first business on its banks will shut its gates this Sunday, November 8. The Eddy, the shipping-container beer garden at 16 S. Sierra St. on the Truckee Riverwalk, is closing for good after ten seasons, the Reno Gazette Journal reported.
The bridge project has already reshaped the corner where Sierra Street crosses the river. For anyone who walks the Riverwalk, floats the whitewater park, or meets friends on the west end of downtown, the next 18 months or more will be shaped by a timeline RTC has already published. The Eddy is just the first place where you can see it.
The Eddy kicked off its final week on Sunday, November 1 with Cafetón and the A.P. Run Club. The morning started with a group run on the boardwalk, followed by specialty coffee, DJs, and reggaetón once the doors opened at 11 a.m. That leaves the weekend:
The venue's FAQ lists hours of 11 a.m. to 10 p.m. Sunday through Thursday and 11 a.m. to 1 a.m. on Fridays and Saturdays, and closing time can shift depending on the crowd. The same page still describes Season 10 as running from March through December 2026. With the closing announcement, that season now ends about two months early.
When it was announced in 2017, The Eddy was billed as Reno's first shipping-container park: an outdoor beer garden with bocce, art, farmers markets, and food trucks, according to KUNR's coverage at the time. Nearly a decade later, owners Kurt Stitser and Phil Buckheart posted a statement about the closing, which News 4 published in full. It names two reasons. One is "the negative business impacts looming from RTC's Sierra Street Bridge project slated to run April 2027 thru Summer 2028." The other is the terms offered for renewing the ground lease.
The bridge is still open, so the closing was decided on the strength of a schedule. The owners also wrote that they hope to "resurface somewhere else in the future," and KOLO's report covers the same two reasons. As of the closing announcement, no new use for the 16 S. Sierra St. site had been made public.
The bridge itself dates to 1937. RTC says it is safe but has outlived its typical lifespan, and maintenance can no longer keep up with its structural condition. The RTC project page shows design at 100 percent and construction expected in spring 2027. The most detailed timeline is in the handout RTC distributed at its August 2026 pop-up event:
| Timing | What happens at Sierra Street |
|---|---|
| Early 2027 | Utility work begins; bridge stays open with minor traffic control |
| March 2027 | Bridge closes; active construction starts on the northern supports |
| July to October 2027 | In-river work |
| Early July 2027 | Demolition of the northern section of the bridge begins |
| Late July 2027 | Demolition of the southern section begins |
| Winter 2027 to 2028 | Large horizontal support beams, called girders, are placed |
| 2028 | Anticipated completion, weather permitting |
RTC's closure date is March 2027, about a month before the "April 2027" in The Eddy's statement. The handout also notes that the project "could extend beyond the anticipated completion date." The project FAQ explains the uncertainty. RTC uses an estimate of 18 to 24 months to set public expectations, while its designer and contractor look at refinements that could cut construction to 12 to 18 months. In-channel work is limited to July 1 through October 31 to protect federally protected fish species, though permitting agencies may allow extra time depending on river flows. If flows get too high, crews have to pull out of the floodway until the river drops.
For a downtown resident, that means the corner could see disruption over more than one summer. RTC expects in-water work to happen within that July-to-October window "for up to 2 consecutive years."
The whitewater park is where the change will be most noticeable on a hot afternoon. The FAQ says most of the park sits upstream of Sierra Street and stays accessible. Recreation is restricted inside the construction zone, and people won't be allowed under the bridge. During construction, signs will direct river users to these exits, in this order:
If you float from Wingfield and usually ride the current past Sierra Street before getting out, plan to get out sooner while the work is underway.
City Plaza had already come up in The Eddy's story earlier this year. On May 21, 2026, Buckster LLC, doing business as The Eddy, submitted a proposal to lease, with an option to buy, City Plaza at 30 N. Virginia St. and an adjacent Redevelopment Agency parcel. The plans included a bar and lounge, a food-truck court, a pizza restaurant, pickleball courts, a children's area, and a stage.
As This Is Reno reported on July 1, the proposal was withdrawn that same day. A memo from the city manager explains that City Plaza is designated in city code as a public plaza and as a space for First Amendment expressive activity. Those designations made commercial leasing or a sale legally difficult. The adjacent parcel didn't carry the same designations.
So the river frontage on both sides of Sierra Street was in play this year. The upstream site is losing its tenant, and the downstream plaza stays public. That's the same plaza RTC will rely on as an emergency river exit while the bridge is being rebuilt.
RTC's design is a two-span, Art Deco-inspired bridge meant to match the look of the corridor. Most of the changes help people on foot:
The FAQ also points to the city's Wingfield and Barbara Bennett Parks master plan. It includes a future in-water path from the new Sierra Street ramp back up to Wingfield Park, so river users could return upstream without crossing the street.
For businesses along the work zone, RTC's FAQ says the closure areas have been adjusted to keep key spots open to pedestrians, and the contractor has to post wayfinding signs and signs encouraging people to support local businesses. The project uses federal money, and the FAQ explains that under the federal Uniform Act, RTC does not pay adjacent businesses for lost revenue.
These are the spots within a short walk of the bridge that were open earlier this year:
Winter hours on the river can change, so it's smart to check each spot before you head over. The next date on the Riverwalk is Saturday, November 21. The Riverwalk District calendar lists Rush the River from 8 a.m. to 5 p.m. with local food and shopping, plus the monthly Wine Walk from 2 to 5 p.m. for $30.
Sierra Street is getting a new bridge and new routines along with it. If you're thinking about where you want your home base downtown while the bridge is rebuilt, Jena Lanini knows these blocks of the Riverwalk and would love to help you find a spot that suits the way you live here. Discover Elevated Living. Start Your Search.